Each year CDS Co-operatives undertakes a range of cyclical and planned maintenance programmes to the homes it owns and also carries out work on behalf of other client co-operatives. Check here to see if your co-op is due for maintenance.
The programme set out below is the current programme for 2009-10. The programme will be updated as new schemes are added to the programme.
CDS Co-operatives - Confirmed Programmes
|
Phoenix Place |
Phase 1 |
Bathrooms |
Planned Sept 2011 |
|
Normandy |
|
Windows |
Planned May 2011 |
|
Normandy |
|
Kitchens Phase 2 |
Planned April 2011 |
|
Phoenix Place |
All rented homes |
Electrical Rewiring |
On site |
|
Temeraire |
All flats |
External redecoration |
Deferred to 2010 |
|
Baltic |
Flats |
External redecoration |
Deferred to 2010 |
|
Phoenix Place |
All |
External redecoration |
Planned Spring 2010 |
|
Harold Campbell Court |
All |
External redecoration |
Planned Spring 2010 |
|
Client Co-operatives where CDS Co-operatives is project managing the work |
|||
|
Weybank |
All homes |
External decoration |
Completed |
|
Lynsted |
6 homes |
Boiler replacements |
Completed |
|
Delce Manor |
All homes |
Roadway repairs |
Completed |
|
Hourglass |
All homes |
External redecoration |
Completed |
|
Senacre |
All homes |
Fencing renewals |
Completed |
|
Colyers Lane |
Flats |
External redecoration |
Completed |
|
Bonham & Strathleven |
All homes |
Boiler renewal |
Completed |
|
Edward Henry House |
All homes |
Kitchen waste pipes |
Completed |
|
Senacre |
All homes |
Bathroom replacements |
Completed |
|
|
|
|
|
|
Brighton Buildings |
All homes |
Windows, baths, kitchens, roofs |
On site |
|
Shenley Church End |
All homes |
New windows and doors |
On site |
|
Weybank |
Various |
Gas central heating |
On site |
|
|
|
|
|
|
Shearwood |
All flats |
External redecoration |
Planned Spring 2010 |
|
St Georges Church |
All homes |
Security works to car park |
Planned January 2010 |
|
Shorncliffe |
Houses |
Kitchens (Phase 3) |
Possible March 2010 |
|
Deptford |
All homes |
Rewiring |
Planned Spring 2010 |
|
Oast Wood |
All homes |
Kitchens |
Planned February 2010 |
|
Milldale |
Flats/Houses |
Bathrooms |
Planned Spring 2010 |
|
St Georges Church |
All homes |
External redecoration |
Planned spring 2010 |
|
Phoenix Place |
All homes |
External redecoration |
Planned Spring 2010 |
|
Delce Manor |
All homes |
Kitchens |
Possible Spring 2010 |
|
Golden Hill |
Various |
Kitchens (Phase 1) |
Possible Spring 2010 |
|
Allnutt Mill |
All homes |
Kitchens |
Possible Spring 2010 |
For more information please contact the Development and Maintenance Administrator at CDS Co-operatives on 03333 21 30 30 or daniel.atkinson@cds.coop